The extremely tremendous essential thermal Rampal Energy plant is predicted to kick off its first unit in July this 12 months so as to add 660 MW to the nationwide energy grid whereas it’s set to go on full-fledged operation in November producing a complete of 1,320 MW.
“With following the federal government’s strict environmental coverage, the 1,320 MW Moitree Tremendous Thermal Energy Mission (Rampal) is being applied with monetary and technical assist of India,” an official conversant in the method advised BSS right here immediately.
He mentioned as per the schedule authorities of the mission have anticipated to begin operation of its first unit having a era capability of 660 MW from July, whereas the second unit with similar capability will start era from November.
In accordance with the mission, Bangladesh-India Friendship Energy Firm Restricted (BIFPCL), a three way partnership firm, has been setting up the facility plant.
It mentioned the bodily progress of the mission until March 2022 is over 79.30 % and the monetary progress is 76.1 %. The cumulative value of the mission is Tk. 12,175.27 crore.
“We’re very a lot involved about setting as our Prime Minister strongly suggests defending nature and setting in implementation of any uplift tasks within the nation,” State Minister for Energy, Power and Mineral Sources Nasrul Hamid advised BSS.
He mentioned the federal government achieved super success in energy sector because it ensures cent % electrical energy protection. Attaining such a giant success has been doable on account of dynamic management of Prime Minister Sheikh Hasina, he added.
Hydro check of boiler mixed, feed discharge and deaerator and many others, of the primary unit have been accomplished on February 20, 2022 and chemical cleansing was accomplished on March 16, 2022. The air tightness check of reheat piping has been accomplished, whereas boiler insulation and portray work can be accomplished quickly.
Turbine Generator 1 Rotor alignment and varied elements of insulation and lube oil flushing have been accomplished. Floor rubber lining of FGD 1 Absorber Tower was accomplished on April 6, 2022. Chimney Flu Can becoming a member of was accomplished on March 30, 2022. Auxiliary boiler commissioning has been accomplished.
Needed works associated to boiler steam blowing and light-up is in progress. Demineralization (DM) and pre-treated water manufacturing is in operation. Coal storage path structural erection and belt laying of conveyor 2,3,4,5 have been accomplished. Coal Shed-1 and Limestone Shed Construction Erection has been accomplished. Erection and commissioning of switchgear and repair transformer at completely different locations is in progress.
Limestone ball mill placement and inside rubber lining have been accomplished. Work is underway for ship unloading, major screening home, mixing silo, crusher home, fly ash and backside ash hopper, silo and ash dyke. Transport air compressor erection has been accomplished.
Apart from, air leak check of Unit 2 of boiler drainable hydro circuit has been accomplished. Erection of coal mill, coal bunker, ID followers, PA fan-1, FD fan-1 and many others, has been accomplished. HP turbine erection and LP turbine field up of turbine generator-2 has been accomplished. Tools erection of cooling tower 2B has been accomplished.
The 230 KV double circuit transmission line (24 km) has been accomplished for energy evacuation. Line charging has been accomplished on August 29, 2021, 230 KV GIS charging on September 9, 2021 and start-up transformer charging on September 26, 2021.
Erection of 400 kV GIS module is in progress. The work of 400 KV double circuit transmission line (173 km) is being applied by PGCB, out of which the civil work of seven piers for laying transmission line (7.4 km) of Padma River crossing part is being applied by Padma Bridge Authority.
Earlier, March 3, 2022, coal buy and provide contract to the mission jetty has been signed. The coal provide will begin when the coal dealing with course of can be prepared.
The settlement to buy limestone and provide it to the mission jetty for sulfur elimination in environmental safety was executed on April 6, 2022.
A Joint Enterprise Settlement (JVA) was signed on January 29, 2012 and the fairness funding was 50:50 ratio. The mission value estimated at Taka 16,000 crore, of which ECA financing Taka 12,800 crore.
Bangladesh Energy Improvement Board (BPDB) and NTPC Ltd., India (Fairness) offering Tk.1,600 crore every. Energy Buy Settlement (PPA) was signed with BPDB for 25 years.
Bharat Heavy Electricals Restricted (BHEL), India is working because the EPC contractor.